Contacts
Local contacts
Collaborators
Phonebook
Useful numbers
Links
Research
Highlights
Publications
Conferences
Image gallery
Users' area
Submitting a proposal
Sample suitability
Beamtime schedule
Shipping goods
Access request
Retrieving data
Manuals
Troubleshooting
Beamline procedures
Microscope procedures
Acquisition software
Data analysis
Spare lists
 
last update 15/02/2010
about | disclaimer

 Microscope procedures 

Operating procedures
Sample transfer
Microscope Alignment Procedure
LEEM operation mode
XPEEM operation mode
Diffraction operation mode
Dispersive plane mode
  Maintenance
Venting
Pump down
Preparing a bake-out
Outgassing after bake-out
Channelplate HV ramping
SPELEEM analyser HV ramping
Prep chamber manipultor wiring

CHANNELPLATE HV RAMPING

In normal operations, when you power up and turn off the detector, take care NOT to have a difference of more than 5 kV between MCP and SCREEN. The following conditioning procedure is to be followed only after venting and bake-out.
  1. Apply voltage to the phosphor screen (Va) in +250V, 1 minute increments. Stop at +1.0 kV.

  2. Apply voltage to the channelplates (Vo) in +100V, 2 minute increments. Stop at + 1.0 kV.

  3. Increase the voltage to the phosphor screen (Va) in +100V, 5 minute increments to +3.0 kV. Wait 5 minutes.

  4. Increase the voltage to the phosphor screen (Va) in +100V, 10 minure increments to +4.0 kV. Wait 5 minutes.

  5. Simultaneously increase the voltage to the phosphor screen (Va) and to the channelplates (Vo) in +100V, 10 minute increments to +5.5 kV at Va and +1.4 kV at Vo.

Total time about 6 hours.